BESS | Commissioning
BESS | Commissioning
Over 6 GW of BESS commissioning delays in the US Commissioning phase is a critical step in the value chain of BESS US BESS sites by status in Q3 2023
Megawatt (MW)
Megawatt hours (MWh)
BESS in operation (Q3 23)
13,477 MW
38,337 MWh
BESS installations ((Q1-Q3 23)
4,393 MW
13,142 MWh
BESS installations Q3 23
2,142 MW
6,227 MWh
BESS under construction
8,134 MW
23,000 MWhe
BESS under construction or in advanced development
21,445 MW
62,109 MWh
Time pressure during commissioning causes errors
BESS project delays
Incentive for fast commission, due to high penalties for delays In ERCOT, 50% of revenue comes from the top 50 days according Modo Energy Commissioning reports lack of battery detail
Key Takeaway: Internal pressure is high to complete 6,160 MW
Source: Clean Power, Modo Energy
Responsibilities and risks are transferred from contractor to client Substantial financial risk linked to the commissioning phase of BESS
17,500 MWh
commissioning projects on time which can lead to compromises on performance and safety. Impact of commissioning delays is high on the project return-on-investments.